Mainstream was recently approached by a Class A office building in midtown Manhattan about replacing one of their air handling units.

Project Installation

The replacement had to be completed over the course of a weekend. Any longer would not be acceptable. In addition to this time restriction, access to the space was tight, so the preexisting unit had to be completely disassembled to be removed. When moving the new unit in, it had to be able to be completely broken down to be delivered.

Installation Time

For Mainstream, these issues were no problem. We manufactured and delivered a modular knockdown unit that fit the existing space and supplied prefabricated pipe headers and ductwork to reduce the installation time. By working with a local contractor for the installation, the building’s tenants could use air conditioning on Monday morning.
 